CONSTRUCTION OF NOVI SAD - BEGEČ BICYCLE LANE/PATH FROM SIME MATAVULJA STREET IN NOVI SAD TO DUNAVSKA STREET IN FUTOG

CONSTRUCTION OF NOVI SAD - BEGEČ BICYCLE LANE/PATH FROM SIME MATAVULJA STREET IN NOVI SAD TO DUNAVSKA STREET IN FUTOG

The bicycle path/lane Novi Sad - Begeč belongs to one of the three corridors that pass through Serbia, the EuroVelo 6 Corridor, from the Atlantic to the Black Sea - a project of the European Cycling Federation, which is developing 14 international cycling corridors into a network that covers the European continent.

In the past period, the works on the construction of the first two phases of the Novi Sad - Begeč bicycle path/lane were completed, as follows:

  • Construction of the bicycle path/lane Novi Sad - Begeč 1st phase (l=1,727 m)

  • The value of the works made around 24.5 million dinars.

  • Construction of the bicycle path/lane Novi Sad - Begeč 2nd phase (l=4,548 m)

  • The value of the works made around 71.8 million dinars.

During October 2022, the construction of the 3rd Phase of Novi Sad - Begeč bicycle path/lane from Sime Matavulja Street in Novi Sad to Dunavska Street in Futog (l=10,573 m) was contracted in the amount of 170.6 million dinars, with co-financing from the Capital Investments Department of the Autonomous Province of Vojvodina, in the amount of 85 million dinars.

The subject of the contract is the construction of a bicycle path/lane on the section from Sime Matavulja Street in Novi Sad to Dunavska Street in Futog, with a total length of 10.5 km. The works are proceeding in accordance with the planned dynamics, and the completion of the works according to the Contract is planned for July 5th, 2023.